[openib-general] InfiniBand 2.6.17 merge plans
Dan Bar Dov
bardov at gmail.com
Wed Mar 29 00:28:17 PST 2006
On 3/27/06, Roland Dreier <rdreier at cisco.com> wrote:
> As we enter the second week of the 2.6.17 merge window, I thought it
> might be helpful to give an update on what I'm thinking about the
> remaining pending pieces. This is really to stimulate discussion --
> if there's something that you think really should (or shouldn't) be
> merged, let me know.
<snip>
> - iSER. Maybe ready to merge -- I haven't heard anything recently.
>
iSER needs to complete the removal of the dummy socket provider
and change the open-iscsi user-space interface.
We are coordinating this effort with open-iscsi, and rely
on some open-iscsi changes that are planned to be pushed to 2.6.18.
Therefore the plan for iSER is to push it into 2.6.18
Dan